The percentage you add to a measured quantity before you order. These are the figures the trades actually use, and they are the same ones built into the 20 calculators on this site. Free to copy, print, or link.

MaterialStandard wasteIncrease it whenWhy this number
Concrete (slabs, pads, footings)10%15% on rough or sloping subgradeA half-inch dip across a 12×10 slab swallows ~5 cu ft. Running short mid-pour creates a cold joint you cannot fix.
Concrete (post holes)1 extra bag per 10 holes20% if you are hand-diggingHand-dug holes are never the diameter you planned. Bell-shaped bottoms drink more than the cylinder math predicts.
Gravel & crushed base5–10%15% over soft or clay subgradeCompaction is the whole point of base rock, and compacted depth is always less than loose depth.
Bedding sand5%10% if screeding by eyeScreeding pushes sand ahead of the rail. What runs off the edges does not come back.
Brick5%10% with many cuts, corners, or curvesCovers breakage in transit, culls, and cut waste. Buy from one production lot; color varies between lots.
Retaining wall block5%10% on curves or stepped runsCurves force angle cuts on the inside radius, and every corner eats a block.
Mulch0%10% if the beds are irregularYou are buying to a depth, not an area. Order the depth you want and it settles into itself.
Topsoil15%20% for finish gradingSoil settles 10–20% after watering. This is settlement, not spillage, and it is the number people forget.
Sod5%10% with curves, tree rings, sprinkler headsEvery curve means a cut, and sod offcuts dry out too fast to reuse elsewhere.
Paint0%, but round up to the gallonAdd 25–30% coverage loss on textureCoverage is the real variable, not waste. 350 sq ft/gal assumes smooth, previously painted wall.
Epoxy floor coating10%20–30% more on the first coat over bare concretePorous slabs drink the primer coat. Running out mid-floor leaves a lap line you cannot blend.
Drywall10%15% with many openings or angled wallsWaste is mostly the offcuts around windows, doors, and the last piece in a run.
Tile10%15% diagonal or herringbone · 20% small or busy roomsEvery border tile is a cut, saw breakage is real, and one bad cut in large format costs 4 sq ft.
Laminate & vinyl plank8%12% diagonal or chopped-up floor plans · never below 5%The offcut ending one row often cannot start the next. One box of a discontinued color is an expensive hunt.
Baseboard & trim10%15% with many cornersMiters and copes consume length at every corner, and short offcuts are rarely reusable.
Fence pickets5%10% with cedar or rough-sawn stockSplits, cups, and culls. Posts and rails you count exactly, plus one post per corner, end, and gate side.
Deck boards10%15% for diagonal or picture-frame layoutsButt-joint cutoffs plus culled boards. Matching board length to deck length gets you near zero.
Deck stain0%, buy by coverageWeathered wood absorbs nearly twice smooth woodCoverage swings from 250 sq ft/gal on sealed wood to 125 on dry, weathered decking.
Roof shingles10%15% with hips, valleys, or dormersEvery valley and hip is a diagonal cut down the length of the run.
Hardwood lumber20–30%30%+ for figured or rustic gradeKnots, checks, sapwood, grain matching, and milling all cut into yield. You buy board feet, you use fewer.

The two rules behind every number above

1. Waste is not padding. It is the material that physically cannot end up in the finished job: the cut piece at every wall, the tile that cracks in the saw, the board with a knot where the joint lands, the concrete that fills a low spot you could not see. Order the measured quantity exactly and you will come up short, every time.

2. The cost of being wrong is lopsided. Over-ordering costs you the price of the extra material, and often not even that, since most suppliers take back unopened boxes and bulk material has a second use. Under-ordering costs you a second trip, a second delivery fee, a stalled crew, a visible seam where the work stopped, and sometimes a dye lot or production run that no longer exists. The asymmetry is why every trade rounds up.

Where waste factors do not apply

Some materials are bought by coverage rather than area, and there the variable is absorption, not waste. Paint, stain, and sealer all fall in this group. A gallon of stain covers 250 sq ft of smooth sealed wood and 125 sq ft of dry weathered decking, so the honest answer is to judge the surface, not to add a percentage. The same is true of primer on new drywall and the first epoxy coat on bare concrete.

Bulk landscape material is the other exception. With mulch and gravel you are buying to a depth, so what matters is measuring the area properly and deciding the depth deliberately. Topsoil is the odd one out: its 15% is settlement rather than waste, which is why it is the figure most people miss and then wonder why their finished grade came in low.

A note on rounding

Every figure here gets applied before you round up to whatever unit the material is sold in: the bag, the box, the bundle, the pallet, the stick, the square. A 2% shortfall against a 50 lb bag of thinset is still a whole bag you have to go buy. Apply the percentage, then round up to the purchase unit, and never the other way around.